15.You are the project manager for the NHQ Project and are working with Patty, a junior project
manager on the project. Patty is curious about the project's critical path and the concept of float.
Patty doesn't understand what the critical path is. Which one of the following statements best
describes the critical path?
A. It's the path that contains the riskiest project activities.
B. It's the path in the project network diagram with the most important activities.
C. It's the path in the project network diagram that reveals the earliest date the project can be
completed.
D. It's always the one path with the least amount of float.
Answer: C
16.You are the project manager of the BGY Project. A new issue has been identified in the project
and this issue could prove to be costly for the project. The issue affects Anna's project deliverable
and she is a negative stakeholder for the project. Considering these elements of the project, what
type of communication would be the most effective to share this news with Anna?
A. Documented review of the issue
B. Face-to-face meeting
C. Informal presentation meeting
D. Immediate telephone call
Answer: B
17.You are the project manager of the NGH Project and are predicting the costs for your project work.
You have determined that an activity in your project has the following cost attributes assigned to it:
Optimistic - $3,500; Most Likely - $7,500; Pessimistic - $12,500.
What is the amount that you'll record for the project's cost in the cost management plan and
estimate?
A. $7666
B. $12500
C. $3500, $7500, $12500
D. $7500
Answer: A
18.Which of the following types of floats are available? Each correct answer represents a complete
solution. Choose two.
A. Half float
B. Free float
C. Full float
D. Total float
Answer: B,D
manager on the project. Patty is curious about the project's critical path and the concept of float.
Patty doesn't understand what the critical path is. Which one of the following statements best
describes the critical path?
A. It's the path that contains the riskiest project activities.
B. It's the path in the project network diagram with the most important activities.
C. It's the path in the project network diagram that reveals the earliest date the project can be
completed.
D. It's always the one path with the least amount of float.
Answer: C
16.You are the project manager of the BGY Project. A new issue has been identified in the project
and this issue could prove to be costly for the project. The issue affects Anna's project deliverable
and she is a negative stakeholder for the project. Considering these elements of the project, what
type of communication would be the most effective to share this news with Anna?
A. Documented review of the issue
B. Face-to-face meeting
C. Informal presentation meeting
D. Immediate telephone call
Answer: B
17.You are the project manager of the NGH Project and are predicting the costs for your project work.
You have determined that an activity in your project has the following cost attributes assigned to it:
Optimistic - $3,500; Most Likely - $7,500; Pessimistic - $12,500.
What is the amount that you'll record for the project's cost in the cost management plan and
estimate?
A. $7666
B. $12500
C. $3500, $7500, $12500
D. $7500
Answer: A
18.Which of the following types of floats are available? Each correct answer represents a complete
solution. Choose two.
A. Half float
B. Free float
C. Full float
D. Total float
Answer: B,D
19.In what organizational structure is the project manager often referred to as a project coordinator or
expeditor?
A. Weak matrix
B. Balanced matrix
C. Projectized
D. Strong matrix
Answer: A
20.You are the project manager of the NHQ Project for your organization. You are working on
creating the project management plan for the NHQ Project and need to identify the costs of the
resources needed in the project. All of the following are examples of resources except for which
one?
A. Network cable
B. Software
C. Staffing management plan
D. Electrical engineer
Answer: C
expeditor?
A. Weak matrix
B. Balanced matrix
C. Projectized
D. Strong matrix
Answer: A
20.You are the project manager of the NHQ Project for your organization. You are working on
creating the project management plan for the NHQ Project and need to identify the costs of the
resources needed in the project. All of the following are examples of resources except for which
one?
A. Network cable
B. Software
C. Staffing management plan
D. Electrical engineer
Answer: C